Receiving inspection confirms whether the goods match the order and whether there is visible damage. On its own, it cannot prove the equipment will perform correctly once installed in the system.
Check identity first
Record the order line, tag number, model or serial number, quantity ordered, quantity received, packing condition and photo numbers. Work from the approved supply list, not an early quotation that may have changed. Keep the labels and packing records.
Without dismantling the equipment, check the visible condition of pumps and valves, the end protection covers and the accessories. Manuals and test documents must match the actual configuration. Record missing accessories and equipment damage separately so the follow-up action is clear.
Escalate issues with evidence
State what was seen, when it was found and which tag it affects. Quarantine suspect equipment for review according to site procedures; do not power it up or pressurize it just to “see if it works”. Acceptance testing needs a separately approved procedure.
Send KFE a discrepancy list and photos organized by tag number, and we can coordinate the follow-up. Checking quantities and documents supports handover, but contractual acceptance and safe commissioning are separate decisions.